Checking Contractor RAMS Before Work Starts in Ireland

In Ireland, a contractor’s risk assessment and method statement can arrive neatly bound, get signed for, and still never be tested against the site in front of you. Filing the document proves it was collected, but it does not prove the client has checked whether the proposed scope, controls, interfaces, and sign-off make sense for the work and the hazards actually present.

This guide is about closing that gap before work starts. It treats approval as a decision, not a receipt, and it gives you a short, repeatable review you can use across contractors. The Safety, Health and Welfare at Work (Construction) Regulations 2013 (S.I. No. 291/2013) provide the regulatory backdrop, but the practical question is simpler: does this risk assessment and method statement address this site, this work, and the other trades around it?

You will learn why filing a RAMS is not the same as reviewing one; what your role is and is not; what to have ready before you open the document; and four checks covering scope match, interface hazards, adequacy of controls, and sign-off. You will also see how to make the review repeatable and turn approval into a clear decision.

Filing a RAMS Is Not the Same as Reviewing One

A familiar pattern: the risk assessment and method statement arrives by email, is dropped into a project folder, and is not opened again until an incident or an inspection asks for it. That is filing, not review.

Filing proves the document exists. Reviewing proves it addresses the site in front of you, the trades already working on it and the sequence the work will actually follow. The gap that matters is rarely document quality. It is document fit: a well-written RAMS for a different job, a different building or a different sequence is still the wrong RAMS. Templates record a snapshot rather than a decision, so it is worth knowing where templates fall short.

What follows is practitioner guidance on testing a submitted RAMS. It is not a legal reading of the Construction Regulations, and it does not replace advice on your own obligations.

The output of a real review is a decision with a reason attached: approved, approved with conditions, or returned with specific queries. That decision, dated and recorded, is what makes approval defensible months later.

What Your Role Actually Is, and What It Is Not

The contractor writes the method statement for its own trade. You test that document against the site. Nobody expects you to author safe systems of work for someone else’s work.

The governing instrument in Ireland is S.I. No. 291/2013, and the HSA’s Construction Regulations 2013 page sits alongside its client duty-holder guidance as the place to confirm what applies to you. For a site-level view, this compliance guide for Irish site managers covers where gaps commonly appear.

Your side of the equation is the site itself: access, services, occupied areas, other contractors, storage, welfare and emergency arrangements. A contractor cannot know these and cannot write around them.

Whether your works count as a “project” under the 2013 Regulations is a legal question, not a box-ticking one. Confirm it with a competent adviser before you assume a duty does or does not apply.

Evidence the review too. A dated record with a named reviewer is usually worth more than an excellent review nobody recorded. With that division clear, the next step is to have the right material in front of you before the RAMS lands.

Before You Open the Document: What to Have in Front of You

With your role clear, the review starts before you read a word of the submission. Have five things in front of you.

First, the current RAMS, dated and versioned. A template recycled from another project, or a document with no date, is not ready to review.

Second, the scope you actually engaged: the tender, purchase order or work order, and the programme. You are comparing what was bought with what the document describes.

Third, a site picture for the same week: who else is on site, what you control, which areas are occupied, where deliveries arrive, and which services can be isolated.

Fourth, your own site rules the RAMS must line up with: induction, permits to work, hot works procedure, isolation process and any client-side risk assessments. Use a repeatable onboarding workflow to check credentials and inductions.

Fifth, name the person who will approve, confirm their competence, and confirm their authority to stop the work if the document does not pass. Without that, review is advice, not a decision.

With those five items assembled, the first check is scope.

Check One: Does the Scope Match the Work You Have Let?

With the RAMS, the work order and the programme side by side, your first test is whether the document describes the job you actually bought. Look for the locations, quantities, plant, access arrangements and duration as commissioned. A document that describes the trade in general has not described this job.

Scope gaps run both ways. Work in the RAMS you never asked for is a cost and coordination problem. Work you asked for that is missing is a safety problem: it will happen anyway, just without a method.

Site-specific tasks should appear by name, for example work at height over an occupied area, hot works near combustibles, excavation near services, work inside a live plant room, or work in a public-facing entrance. If none are named, the document probably came from another site.

A weak answer looks like a method statement with no site address, a sequence that contradicts the programme, or “as per manufacturer instructions” standing in for an actual method.

Where the work is split across subcontractors, each RAMS should state what it covers and what it leaves to others. Those boundaries must meet without leaving a gap in the middle. Check the supporting paperwork in the same pass, so the induction records Irish sites should hold are ready before a crew arrives.

Check Two: Are the Interface Hazards With Other Trades Covered?

Scope match clears what is being done. Interfaces test whether it can be done alongside everyone else. This is where filed-but-untested RAMS tend to come apart: two contractors each submit a reasonable method statement, yet contradict each other on access, isolation or sequence.

Test the overlap points explicitly: shared access routes and scaffolds, isolations and permits, deliveries and lifting, waste removal, welfare facilities, and emergency arrangements. Ask each trade to name the other trades it depends on and what it needs from them. Then check the other document says the same thing. Two documents that assume different things create an incident waiting on a schedule.

“Coordinate with the main contractor” or “as directed on site” is a weak answer. A useful interface control names the other party, the action and the moment it happens, for example who controls a shared scaffold handover or when a permit is released.

Treat any change in site layout as a trigger: a new crane position, closed escape route, relocated compound or second crew arriving. Re-check the interface controls rather than assuming the old document still covers it. The same discipline keeps your own Irish employer safety statement guide current.

Check Three: Are the Controls Adequate and Specific to This Site?

Once the interfaces are settled, ask whether the controls behind them would hold on this site. A control is adequate when it is specific, assigned and verifiable: a stated action, done by a named role, by a stated point, with evidence afterwards that it happened.

Check the hierarchy. Elimination, substitution and engineering controls should be considered before the document leans on PPE and behaviour alone. Then read the risk ratings. If every hazard sits at the same level with no explanation, the assessment has not been used to make a decision; it has filled a column. For a practical way to interrogate the ratings, see hazard analysis and risk assessment.

Hypothetical weak answers include a control that restates the hazard (“be careful near the edge”), a blank box where the responsible person should be, or an emergency plan that stops at “call the emergency services”. As a final test, pick the three worst things that could happen on this site and check the document contains a control for each, written for this site rather than for the trade in general.

Check Four: Who Signs Off, and What Does the Record Prove?

Adequate controls only mean something once someone with the authority to accept them has done so. Decide who approves before the document arrives: one named person whose competence matches the work beats a circulation list where everyone assumes someone else read it. Record the document version and date, the reviewer, the review date, what was queried, what changed and what was accepted with conditions.

Conditional approval is legitimate. Allowing one section to start only once an isolation certificate is issued is reasonable, provided the condition is written down and its completion is confirmed before work begins.

Weak answers are easy to spot: an email saying “looks fine, go ahead”, a signature on a cover sheet with no version reference, or verbal approval on a phone call. None of these prove which document was reviewed or what was decided.

Approval is not permanent. A change of scope, crew, plant or programme should send the RAMS back through all four checks. As with COSHH assessments, the review triggers that matter include who owns the review and how you prove it happened. Treat sign-off as a dated decision, not a formality.

Making the Review Repeatable Across Every Contractor

The four checks only pay off if they run the same way every time. Fix the review point before the start date. A RAMS read on the morning of mobilisation, with the crew already on site, is a notification rather than a control. Set the deadline days out, not hours.

Apply the same four checks to every submission, on the same review form, whatever the trade or size of job. Our Compliance Genie digitises your health and safety processes, and the Health and Safety App keeps the same review form in one place; the four checks stay the reviewer’s job. Repetition turns review into a habit, gives you a checklist for contractor compliance that stays comparable from one contractor to the next, and makes a conditional approval defensible months later.

“Needs more detail” invites a second review round, so give the contractor answers in writing.

The record’s value is showing what you knew and what you decided when you allowed work to start.

Software such as the Contractor Genie can keep contractor records and site visits in one place, but it does not read the RAMS for you. The technical judgement stays with the reviewer.

Turning Approval Into a Decision

A repeatable review is only worth the habit if it ends in a decision. Run the four checks in order on the next risk assessment and method statement that lands on your desk: scope match, interface hazards, adequacy of controls, sign-off. Read it against the site rather than against the document. The question is never whether the RAMS is well written. It is whether it covers what is actually happening here this week, around the other trades on site.

Return anything that fails, with the specific query and a deadline for resubmission. A returned RAMS holds up the start you had planned, while a filed one that nobody tested leaves you without a clean answer if an inspector or an incident asks for it.

Re-run the checks whenever scope, crew, plant or programme changes, because approval is a point-in-time judgement, not a permanent clearance.

Finally, confirm your own obligations against S.I. No. 291/2013 and the HSA’s client duty-holder guidance rather than relying on a template or on what the contractor tells you. That is what separates an approval that holds up from a receipt in a folder.

Conclusion

Checking a RAMS is not a filing exercise. It is a decision about whether work can start safely this week, given the trades on site and the order the work will follow. The four checks give you a repeatable habit: match the scope, cover the interfaces, test the controls against the site, and confirm who signed off. Record the version, the decision and any conditions, then re-run the checks whenever scope, crew, plant or programme changes.

Your next step is simple. Take the next RAMS that lands on your desk and run the four checks in order before you approve it. Contractor Genie can keep contractor records and site visits in one place, but the judgement stays with you.

An approval that holds up months later starts with a review you can explain today. Make the habit, make the decision, and let the record prove it.